Project overview
A leading pharmaceutical company in Indonesia set out to install a high-capacity boiler within a tight timeline to support growing process demands.
Thermax executed the project with efficient planning and engineering, ensuring rapid installation and commissioning while maintaining high safety standards. The solution enabled faster operational readiness, improved productivity, and delivered significant cost efficiencies.
Challenges
- A leading pharmaceutical company in Indonesia needed to install a
Solution
- Thermax took on the challenge, executing the project with precision planning and expert engineering. The team completed erection and commissioning of the plant in just eight months, four months ahead of schedule. The commissioning was completed in just 40 days, while maintaining the highest safety standards with zero incidents.
Result
- This early completion helped the customer resume operations swiftly, improving productivity and resulting in substantial cost savings through efficient project management and seamless collaboration.
Case study
Thermax’s seawater treatment solution optimises water recovery for process industries
Case study
Thermax’s ETP solution enables sustainable effluent treatment for a palm oil refinery
Case study
Thermax enables a herbal manufacturer to convert waste to low-cost energy
Case study
Thermax’s absorption chiller helps boost operational efficiency in coconut processing
Case study
Thermax’s electrostatic precipitator helps control emissions for a leading biotechnology company
Case study
Thermax’s Bi-Drum FBC boilers and ESP reduce coal usage and emission compliance for a chemical industry
Case study
Thermax enhances gas-to-power efficiency with modular HRSGs for power producer in Indonesia
Case study
Thermax’s pre-treatment system ensures high-quality feed water for process and boiler operations