Case study
Thermax sets a record by installing and commissioning a bi-drum boiler in just 40 days for a pharmaceutical major in Indonesia
Select an option
Project overview
Thermax successfully executed the installation and commissioning of a bi-drum boiler for CJ Bio, a leading pharmaceutical company in Indonesia. The project required rapid execution while maintaining the highest standards of safety, engineering excellence, and project management.
Close collaboration between Thermax and the customer ensured smooth planning, logistics, and on-site execution, enabling timely completion without compromising quality.
Challenges
- The project faced a very tight installation and commissioning timeline. Coordinating logistics, planning, and execution across teams in a short duration was critical. Ensuring strict adherence to safety standards while avoiding rework and maintaining engineering precision added to the complexity of the project.
Solution
- Thermax addressed these challenges through meticulous planning and strong project management. Experienced engineering and execution teams were deployed on site, working closely with the customer to ensure seamless coordination. High-quality execution, strict safety protocols, and technical expertise helped eliminate rework and ensured smooth and efficient project completion.
Result
- The bi-drum boiler was installed and commissioned in a record time of 40 days with zero reported safety incidents. The project achieved 100% excellence in engineering and project management. Early commissioning helped the customer resume operations ahead of schedule, leading to improved efficiency and cost savings.